|
|
|
Capturing Cross-Section Data on Willow Creek |
|
Heppner, Oregon |
|
October 1995 |
|
|
|
|
How much water can be released from Heppner Dam
without flooding local farmland or damaging property? The Corps of Engineers want to know. |
|
|
|
|
|
Cross Sections must be taken at: |
|
Every Bridge Crossing or |
|
Every 300 feet |
|
In City Limits: whichever occurs first |
|
Outside City Limits: at every bridge crossing
only |
|
|
|
|
|
Each Bridge Cross Section Must Be: |
|
Sketched |
|
Photographed |
|
Described |
|
HI measurements booked |
|
Accuracy:
must be within 1/10th foot |
|
|
|
|
|
|
|
|
|
|
|
Trimble 4000SSE GPS Total Station |
|
Consists of: |
|
Base Receiver & Radio |
|
Rover Receiver & Radio |
|
Backpacks |
|
Range Pole |
|
TDC-1 Data Logger |
|
|
|
|
Base 4000 Receiver |
|
Base Radio/Amp |
|
GPS Antenna |
|
Radio Antenna |
|
Two Tripods |
|
Batteries |
|
TDC-1 Data Logger to Start Base |
|
|
|
|
Rover 4000 Receiver |
|
Rover Radio |
|
GPS & Radio Antenna |
|
Batteries |
|
TDC-1 Data Logger w/Survey Controller Firmware |
|
Backpack & Range Pole |
|
|
|
|
Nine Control Points Established Using Static GPS |
|
4 BLM
Monuments Basis of Network |
|
Max. Distance Between Control Points only 3
Miles |
|
|
|
|
Requires Two Independently Obtained Sets of
Coordinate Values (i.e. Lat, Lon, Alt & Northing, Easting, Elev) on
each Point to be Used in Network |
|
|
|
|
|
Four Steps to Calibration |
|
Datum Transformation |
|
Transforms WGS-84 to NAD-83 |
|
Plane Projection |
|
Moves Project to a Horizontal Plane on a Sphere |
|
Plane Adjustment |
|
Provides Rotation, Scale Factor, Triangulation |
|
Height Adjustment |
|
Models Change in Elevation Using an Inclined
Geoid Plane |
|
|
|
|
Allows Us to Work in Local Coordinates in the
Field |
|
Can Instantly Verify Accuracy by Comparing
Observed with Published Coordinates |
|
|
|
|
|
GPS |
|
Maintain Lock with SATS |
|
Monitor Battery Levels |
|
Call back HI Values |
|
Capture GPS Data |
|
Rod Man |
|
Determine Points of Observation |
|
Call out HI Values |
|
Crew Chief |
|
Sketch Bridges & Take Photographs |
|
Keep Notes |
|
Record All Vertical Values |
|
|
|
|
Started Base Receiver |
|
Dam Was Our First Significant Obstruction |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Established Point 25 Feet off Road Surface |
|
Moved Base for the First Time at 10:30am |
|
Verified New Base |
|
Checked Point to North |
|
Checked Point to South |
|
|
|
|
|
|
End of Day Two |
|
Logged 211 Points |
|
Approximately 20 Cross Sections |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Got Out of Heppner Before Noon |
|
Cross Sections Were at Bridges Only |
|
Some Were Thousands of Feet Apart |
|
Data Logging Got Easier (less trees) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TREES |
|
Only had to see SATS for < 10 seconds |
|
Acquired SATS in open, then ran under trees to
collect data before losing lock |
|
|
|
RADIOS |
|
Had to move Base 4 times, rather than twice |
|
Would had better range with more elevated radio
antenna (+15 feet) |
|
|
|
|
|
BATTERIES |
|
Rover batteries lasted only 45 minutes (spec
says 45-90 minutes) |
|
Mixed up charged and un-charged batteries |
|
Base batteries were large enough to last all day |
|
Charger for Base radio battery barely adequate |
|
|
|
|
GPS Data Capture Went Smoothly |
|
Anticipated Use of Conventional Gear |
|
Crew Returned with Conventional Gear Two Weeks
Later |
|
Picked up 9 Cross Sections (90 points) |
|
GPS Point Total: 1020 |
|
Conventional Point Total: 90 |
|
GPS Completed 92% of Project |
|
Finished 17 Days of Work in 6 Days |
|
|
|