Summary
•GPS Data Capture Went Smoothly
•Anticipated Use of Conventional Gear
•Crew Returned with Conventional Gear Two Weeks Later
•Picked up 9 Cross Sections (90 points)
•GPS Point Total: 1020
•Conventional Point Total: 90
•GPS Completed 92% of Project
•Finished 17 Days of Work in 6 Days